HomeLifeMetro workers replaced 180 meters of rails

Metro workers replaced 180 meters of rails

They were replaced in curve 3 of line 3, located between the Plaza Venezuela and Ciudad Universitaria stations.

180 meters of rails on Line 3 of the Caracas Metro were replaced, according to the company's X, indicating that these works are part of the subway modernization tasks, framed in the second phase of the ¡Se Mueve Contigo! Metro Plan.

The 180 linear meters of rails were replaced in curve 3 of line 3, located between the Plaza Venezuela and Ciudad Universitaria stations, during the early hours of this Sunday the 29th.

The action was carried out entirely with Venezuelan labor from the specialized technicians of the general management of Structures and Track Maintenance of the CA Metro of Caracas.

In that sense, the manufacturing was done in the yards and workshops of Propatria, producing 5 segments of rails of 36 meters in length, each of which was transported by flat wagons to the intervention area, where they were installed in compliance with all standards. international quality.

It is important to highlight – the note states – that this type of tasks in the past were carried out by international contractors. However, the training of Camero's human talent has made it possible to comply with the guidelines of the President of the Republic, Nicolás Maduro, to advance towards technological independence, import substitution and foreign currency savings, which has been a flag of the Great Mission. Transportation Venezuela.

The modernization work of the railway will continue until the entire system is completed according to the preventive maintenance schedule programmed by the Structures and Tracks Maintenance management, which are carried out during the early morning hours to avoid affecting the service to the user.