HomeLa Guaira65% complete presents Maya Picure project in La Guaira

65% complete presents Maya Picure project in La Guaira

Despite the complexity of the mountainous terrain, 1.536 meters of 36-inch pipes have been replaced to serve more than 30 thousand families.

65% complete presents the Maya Picure project executed in the state of La Guaira by the Ministry of Water Attention and the Government of the entity to optimize drinking water service.

1.536 meters of 36-inch pipes have already been replaced in the Maya-Picure mountain axis of the state of La Guaira, to increase production from 300 to 600 liters per second of water and benefit more than 30 thousand families.

The information was offered by the ministerial entity in its account on the social network ×1.

“Governor Alejandro Terán and the Hidrocapital workforce are advancing by sea and land, putting their hearts into Maya Picure, to increase water distribution from 300 to 600 liters per second and respond to the 1×10 reports of Good Government ”, he published on the social network.

More than 2.000 meters of pipeline will be replaced in La Guaira

In this regard, the Ministry indicated in a press release that more than 2.000 meters of pipeline will be installed, in a complex area that is difficult to access due to the complexity of the mountainous terrain.

For this, a team is deployed made up of engineers, technicians, specialists and workers who work day and night on the project.

The note details that in the first phase, 888 meters of 36-inch pipe were installed, while in the second phase that is underway, 648 are being installed for a total of 536 meters placed in this complex and difficult-to-access terrain.

Likewise, the difficulty of installing the pipeline stands out because the sections – 12 meters long and weighing 4 tons each – must be towed to the work area by peñeros, and then placed at the points where they will be attached to the pipe. the network with heavy machinery.

In addition, he adds that there are 38 work fronts deployed for replacement, and it is not ruled out that additional sections of pipe will need to be changed to avoid future damage to the adduction.