HomeAnzoáteguiRoad recovery began on the Los Machos-Naricual section in Barcelona

Road recovery began on the Los Machos-Naricual section in Barcelona

9.5 kilometers of road will be paved, in addition to its lighting and demarcation

The asphalt plan that the Barcelona mayor's office has been carrying out has reached the Los Machos-Naricual highway section, where it is planned to place more than 3 tons of asphalt.

It is planned to recover 9,5 kilometers - announced Mayor Sugey Herrera this Tuesday, May 28 from the Los Machos sector - at the start of work on that road that connects the rural parish of Naricual, with the urban parishes of the Simón Bolívar municipality, San Cristobal and El Carmen.

Herrera highlighted that these works will not only benefit the carriers of five lines that provide public service, but also the more than 14 thousand inhabitants of the communities of that territory, merchants and those who visit the rural area for recreational purposes.

Accompanied by the líderes and street leaders of the Valles del Neverí commune, Herrera explained that the scarification of 13 square meters will be carried out to place the asphalt mixture, whose resulting material (gravel) will be used by the communities to improve some streets.

“I know that it is one of the most felt problems, we have the best disposition to do the work of dignifying and improving your conditions, this is a commitment of the Concrete Action Agenda, and the líder"es and leaders must be bearers of this good news," said Herrera.

Likewise, the mayor said that, additionally, in that stretch work will be done on the formation of the soil base, repair of concrete slabs, leveling of manholes, arrangement of water cans and cleaning of the canal that borders the road. as complementary actions.

The local leader indicated that once this section is completed, the demarcation and placement of cat's eyes will be carried out, in addition to the public lighting being rectified.

He recalled that in the first phase of recovery of this road axis, two other important sections were rehabilitated.

The first that goes from the entrance of Mesones to the Mayorquín bridge, 500 meters long, where 1.404 tons were placed; The second includes the stretch from the Mayorquín bridge to the entrance to Naricual, of about 4 linear meters, which required the placement of more than 800 tons of asphalt.