Electricity service was fully restored in the municipalities of Punceres and Bolívar in the state of Monagas, through a technical and institutional deployment that erected three large metal structures to energize nine key circuits.
The governor of Monagas, Ernesto Luna, confirmed the completion of the work carried out. following the emergency caused by a weather event registered in the north of the state on August 18.
The regional leader stated that the multidisciplinary operation, comprised of Corpoelec, Pdvsa, the governor's office, municipalities, and the Armed Forces, intervened along a 1,5-kilometer route in the Tropical sector.
“With the erection of catenary-type towers, anchoring structures and gantries up to 22 meters high in the Isabela Farm, the crews normalized the flow from the Boulevard line, Quiriquire,” Luna said.
The governor of Monagas reported that the gradual restoration of power to the 115/13.8 kV and 115/34.5 kV lines has returned service to 45 communities. In the Punceres municipality, the Miraflores, Azagua, Cachipo, Quiriquire, and Petroquiriquire circuits were reactivated, while in the Bolívar municipality, the Centro, San Vicente, Los Kilómetros, and La Bomba circuits were restored.