The Minister for Transportation, Ramón Velásquez Araguayán, reported that 25% progress was reached in the work to repair the sinking registered this Sunday at Km 1 of the Pan-American highway, which connects Caracas with Los Teques, Miranda state.

Velásquez Araguayán also reported this Monday that the construction work to reduce the canal continued all night.

"Construction work continued throughout the night on Monday morning at Km 1 of the Pan-American Highway. A major effort to pump out the canal was undertaken," he posted, along with photographs showing the scope of the work.

"In less than 24 hours, we reached 25% completion on the construction of Km 1 of the Pan-American Highway. We will continue to provide you with timely information," the Minister of Transportation stated hours earlier via his Twitter account. @rvaraguayan, accompanying a statement explaining that the sinking of the road was caused by the collapse of the sewer system that passes under it.

Here is the full content of the statement:

"Since the early hours of Sunday, July 17, we have been working on Km 1 of the Pan-American Highway, the road that connects Caracas with Los Teques, due to a collapse of the roadway. The collapse was caused by the collapse of the sewer system that runs beneath the roadway.

Today, Sunday, we are in the construction phase, and while the work is being carried out, we suggest that users of this important road artery make use of the different detours from the Altos Mirandinos to Caracas via El Poliedrito, Las Mayas and vice versa.

There are three detours for those who travel along this important road; the first, to deviate through El Poliedro, in both directions, until it exceeds Km 1 where the damage is located. The second, they can use the Las Mayas Distributor for those who go from Caracas to the Altos Mirandinos; and the third option for those who come from Los Teques to Caracas who want to leave through Las Mayas, there are also 3 mechanisms there: the first is using the intersection via La Cascada, in the Don Pedro sector; the second, using the Carrizal bridge; and the third, through San Antonio de los Altos.

There is one last alternative route, a slightly longer route, which is to go down from Los Teques to Tejerías and from there connect with the Autopista Regional del Centro (ARC).

We're doing our best to get things moving again. We'll keep you updated on the progress!

The works have been carried out since the early hours of this Sunday, according to information released by Venezolana de Televisión and ratified by a statement published by the minister on his account.

Permanent monitoring

This Sunday night, the mayor of Caracas, Carmen Meléndez, together with the Minister for Transportation, Ramón Velásquez Araguayán, inspected and certified the progress of the repair work on the Pan-American highway.

Through their account on the social network Twitter, the mayor and the owner of transport expressed that they aspire to complete these works as soon as possible.

"Together with Minister @rvaraguayan, we inspected the works being carried out on the Pan-American Highway, with the participation of @HidroCapital2 and the local community, with the goal of restoring traffic on this road as quickly as possible," Meléndez said.

"...we are trying to complete the work in record time," the Minister of People's Power for Transportation stated on his social media account, along with a video of the inspection.

alternate pathways

This Sunday night, the Minister of Transport informed in contact with VTV, that due to the recovery work on the road, the closure of the road in both directions will continue for the next few hours.

For this reason, he reported that as a contingency measure, three routes for vehicular traffic in the area.

The first route is to deviate through the Polyhedron in both directions until reaching kilometer 1 where the affectation is located.

The second, for those who go from Caracas to Los Teques, is to use the Las Mayas distributor; and for those who go from Los Teques to Caracas and want to exit through Las Mayas, there are three mechanisms: the first is to use the intersection via La Cascada in the Don Pedro sector; the second use the Carrizal bridge; and the third through San Antonio de Los Altos.

The third alternative route, – a little longer according to what Velásquez Araguayán explained -, is from Los Teques down to Tejerías and from there joins the Autopista Regional del Centro.

"We are in the construction phase, and while the work is being carried out, we suggest that the users of this important road artery make use of the diversions," he suggested.

1 COMMENT

  1. Good, it is not about finishing the work in record time, it is about carrying out the work well that lasts over time, the Panamericana is a very important road artery for the different connections that are made through it, so these works must be carried out According to civil ING rules, if 1 or 2 more days are needed, no way, but that the work is well done, I hope that the repair and commissioning are carried out again, thanks