As part of the Venezuela Renace Plan, the Presidential Commission for the Recovery of the Central University of Venezuela (UCV) continues the recovery work of the University City of Caracas.
According to a press release, work is progressing at the Faculty of Architecture and Urbanism (FAU), where the bathroom area is being repaired, and work will later begin on the so-called Galia Workshop.
Likewise, at the Faculty of Engineering, the cracks are being scarified and the frieze demolished to proceed with the final finish, while at the Faculty of Economic and Social Sciences, the roof flashing is being removed and some floor tiles are being lifted.
Regarding the damage to the José Izquierdo Anatomical Institute, masonry repairs are being carried out in the central halls and corridors, as well as in the south wing of the first floor of the Humanities and Education Faculty building.
In the Transfer Building of the School of Education, Administration, and Accounting, cracks are being repaired in hallways, classrooms, and bathrooms, along with the restoration of moldings and light fixtures. Damage to the exterior mosaic and the interior frieze at window level was also reported in the Teaching Laboratories of the Faculty of Sciences.
It should be noted that this commission carried out a series of preventive shoring works in the corridor parallel to Avenida Carlos Raúl Villanueva, the Covered Plaza and an area near the cafeteria of the Swimming Pool Complex, the information bulletin details.
Finally, the development of this engineering technique aims to use temporary supports with metal struts, while the necessary studies for the recovery of the house that overcomes the shadows are carried out, in accordance with the previously established protocol.