Three months after the double earthquake of June 24, the housing response in the affected states is moving towards a stage focused on the rehabilitation of buildings, reconstruction and the search for new solutions for families who will not be able to return to their homes.
In an interview with Últimas NoticiasJacqueline Faria, president of the Venezuela Renace Plan, reported that they have incorporated 18.864 homes into the various work fronts in the affected areas. Of this total, 15.132 are apartments and 3.732 are houses, benefiting 76.737 people.
He explained that as of September 23, 63.160 inspections had been carried out in the states of La Guaira, Capital District, Miranda, Falcón, Aragua, Carabobo and Yaracuy.
According to the report from the Habitable Platform, 36.779 infrastructures were classified with a green label, 14.944 were classified as yellow, and 11.437 received a red label.
Green corresponds to habitable structures, yellow identifies properties that can be used with restrictions and under preventive measures, while red indicates that the building is not habitable and must be subjected to specialized studies to determine if it can be recovered or requires demolition.
Faria explained that this classification allows defining the intervention for each property and linking it to the situation of the affected families.
According to the report presented by the official, 1.815 families have already returned to their homes after the completion of the recovery work and verification of the habitability conditions.
“We are in the phase of consolation, of hope, but also of certainty,” Faria stated, describing the current state of the plan after the initial response to the seismic emergency.

Rehabilitation.
Faria explained that 14 implementing entities are participating in the reconstruction phase, according to the level of damage to each property.
Among the institutions involved are the Venezuela Renace Foundation, the Ministries of Public Works and Housing and Habitat, Venezuela Bella, Juntos Todo Es Posible and the Great Mission Barrio Nuevo Barrio Tricolor, as well as the regional and municipal governments.
Assistance is provided through four modalities. One involves the distribution of material kits for minor repairs; another, the deployment of teams with engineers, materials, and labor for larger-scale interventions. Specialized contractors are also hired for projects requiring technical oversight, and finally, controlled demolitions are carried out when studies determine that a structure cannot be salvaged.
Therefore, the red alert status does not automatically imply demolition. These properties must undergo a second evaluation, with the participation of structural engineers and other specialists, to determine their fate.

Ana Victoria: from red to green.
One of the cases cited by Faria in the state of La Guaira is the Ana Victoria urban development, located in the Carlos Soublette parish.
The complex consists of nine buildings: two were classified as red and the remaining seven as yellow. The official reported that all nine structures have been restored.
The case represents one of the comprehensive interventions developed after the earthquakes, with coordinated work on the buildings and their services, instead of only addressing individual homes.
On September 17, the government reported the completion of 339 rehabilitated homes in Caracas, La Guaira, and Aragua. In the coastal region, 10 houses were completed in La Lucha, 25 in César Nieves, and six in the Catamare housing development. With this achievement, the total number of rehabilitated homes nationwide reached 1.815.
Currently, the Venezuela Renace Plan in La Guaira is carrying out the recovery of the Martín Vegas urban development in the Urimare parish, where 218 renovated and safe apartments will be delivered in the coming weeks.
Recovery and new solutions.
In La Guaira, the recovery combines the repair of structures that can be intervened with the search for alternatives for families whose properties have irreversible damage.
Faria reported that in the state, 1.430 houses and 132 buildings suitable within the habitability categories were identified, with a universe of 4.747 recovered homes and 26.766 people benefiting.
At the same time, technical teams began evaluating land to define possible areas for new housing developments for families who cannot return to their homes.
This policy also includes those who decide to relocate to other states. According to the Habitable Platform census cited by Faria, around 10% of registered families expressed their intention to move and indicated states where they have relatives, including Monagas, Nueva Esparta, and Bolívar.
The official indicated that these cases will be addressed through housing solutions in the destination entities.

Impacted structures.
Faria specified that 675 structures in La Guaira were impacted by the earthquakes, with different levels of damage, while 199 buildings collapsed during the event on June 24.
For buildings that remain standing, the assessment goes beyond determining whether they can be occupied. Structures with major damage must undergo studies on their behavior and the definition of the work necessary to restore them to safe condition.
Therefore, controlled demolition is considered one of the final routes in the process, after completing the technical studies that allow establishing the possibility of rehabilitation.
Safety for new interventions.
The reconstruction also incorporates safety criteria against future seismic activity.
Faria explained that the building codes have been updated based on the experience gained from previous earthquakes and recalled that after the 1967 earthquake, the criteria applicable to new buildings were modified.
The president of the plan indicated that the current interventions seek to increase the capacity of the structures to respond to ground movements, through solutions that allow displacement and structural flexibility without compromising their stability.
The goal is for buildings to be able to withstand seismic activity and provide adequate conditions for the evacuation of their occupants.
This component is particularly important in La Guaira, where recovery is taking place in parallel with assessments of the condition of buildings and the territory.
From emergency to care.
Three months after June 24, the process focuses its efforts on converting the diagnoses made during the emergency into completed works and housing solutions.
The initial response identified the affected structures and established occupancy conditions. The current phase requires completing studies, carrying out repairs, defining necessary demolitions, and moving forward with the construction of housing for the families who lost their homes.
In La Guaira, this process combines the rehabilitation of urban areas and housing with the planning of new developments for those who cannot return. In addition, families who have requested relocation to other states are being offered the option of moving.
The challenge now is to ensure that the classification obtained in the inspections translates into concrete answers for each household: the return to a rehabilitated home, the repair of their property, reconstruction, the demolition of an unrecoverable structure, or the allocation of a new housing solution.
The progress of the Venezuela Renace Plan is beginning to be measured not only by the number of properties inspected in the national territory, but also by the homes recovered, the families that have been able to return and the solutions that are built for those who will not be able to return to their former homes.